[2009] 9 MLJ p.328

ARCTIC BUILDING AND CIVIL ENGINEERING SDN. BHD V AHMAD ZAKI SDN. BHD & ORS
Plaintiff had relied on letters not pleaded it its claims.
Held: The letters of appointment to the plaintiff had categorically showed that it was the third defendant who had appointed the plaintiff to supply sand and earth for the project.A Contract cannot confer rights or impose obligations arising under it to any person except the parties to the contract itself.